Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam VCS-277 topic 1 question 33 discussion

Actual exam question from Veritas's VCS-277
Question #: 33
Topic #: 1
[All VCS-277 Questions]

An administrator has a scheduled policy that backs up 20 clients, each with multiple mount points and multiple data streams enabled. One of the jobs has failed and is in an Incomplete state in the Activity Monitor.
How should the administrator verify the incomplete job runs prior to the next scheduled backup?

  • A. run a manual job for the client
  • B. resume the job
  • C. run a manual job for the mount point
  • D. resume the parent job
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fmatzinger
3 years, 3 months ago
you can't resume a failed job, you can only restart it
upvoted 1 times
Swanie
2 years, 4 months ago
The job i not failed totally. It is in an incomplete state and thus can be resumed. Correct answer is thus B
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in