What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
TDMM page 21-23 (1554)
PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6
PERT = [40h + (4 x 50h) + 60h] / 6
PERT = 50h
upvoted 1 times
...