Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam RCDD-001 topic 13 question 8 discussion

Actual exam question from BICSI's RCDD-001
Question #: 8
Topic #: 13
[All RCDD-001 Questions]

What is the PERT estimate of time for cable placement on a given job?
- Optimistic time is 100 hours
- Most likely time is 125 hours
- Pessimistic time is 210 hours

  • A. 100 hours
  • B. 125 hours
  • C. 135 hours
  • D. 155 hours
  • E. 175 hours
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
CUB90
7 months, 3 weeks ago
TDMM page 21-23 (1554) PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6 PERT = [100h + (4 x 125h) + 210h] / 6 PERT = 135h
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in