Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
TDMM page 21-23 (1554)
PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6
PERT = [100h + (4 x 125h) + 210h] / 6
PERT = 135h
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CUB90
7 months, 3 weeks ago