Exam PSM I topic 1 question 21 discussion

Actual exam question from Scrum's PSM I
Question #: 21
Topic #: 1
[All PSM I Questions]

What is the key concern when multiple Development Teams are working from the same Product Backlog?

  • A. Minimizing dependencies between teams.
  • B. Clear definition of requirements.
  • C. Meeting original scope projections.
  • D. Making sure there's enough work for everyone on every team.
  • E. Maximizing velocity.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
arualpcl
Highly Voted 4 years, 11 months ago
I have doubts as to why the correct answer is not A.
upvoted 21 times
...
Mustermann
Highly Voted 4 years, 2 months ago
The Nexus Guide (https://www.scrum.org/resources/nexus-guide) says on page two: "The work must be organized and sequenced, the DEPENDENCIES RESOLVED, and the outcomes staged." So A should be right.
upvoted 8 times
...
Roliani
Most Recent 2 days, 22 hours ago
A is correct
upvoted 1 times
...
sicario777
1 month, 2 weeks ago
Answer is A. The primary concern when multiple Development Teams work from the same Product Backlog is minimizing dependencies between teams. This is crucial because dependencies can create bottlenecks and impede progress, making it difficult for teams to work efficiently and effectively. By minimizing dependencies, teams can work more independently, reducing the likelihood of delays and enhancing overall productivity. This approach ensures that each team can focus on their tasks without being overly reliant on the progress or completion of tasks by other teams, which is a fundamental aspect of scaling Scrum effectively. https://www.scrum.org/forum/scrum-forum/36163/can-two-teams-work-one-product-backlog
upvoted 1 times
...
Djedjig
4 months, 2 weeks ago
A is correct
upvoted 1 times
...
mediafreak
6 months, 1 week ago
A is the correct answer. This question confused me at first. With the Scrum Guide v2020, there is no longer a Developer Team. There are the developers and the Scrum team. The key challenge is to minimize dependencies between the scrum teams
upvoted 1 times
...
Pat_PMP
6 months, 3 weeks ago
Selected Answer: B
This is a trick question. "Key concern". It's about order. You cannot minimize dependencies without clear definition of requirements. So B: Clear definitions trumps A: minimizing dependencies.
upvoted 2 times
...
Mi_Windsor
6 months, 3 weeks ago
A is the correct answer, from Nexus's guide
upvoted 1 times
...
wax_gibbous
8 months ago
Selected Answer: A
According to NEXUS: "Cross-Team Refinement of the Product Backlog reduces or eliminates cross-team dependencies within a Nexus. The Product Backlog must be decomposed so that dependencies are transparent, identified across teams, and removed or minimized."
upvoted 3 times
...
Prozac400
8 months, 3 weeks ago
When multiple Development Teams are working from the same Product Backlog, a key concern is minimizing dependencies between teams. This helps ensure that each team can work independently and deliver value without being overly reliant on the work of other teams. Reducing dependencies allows for greater flexibility and efficiency in delivering increments of the product during a Sprint. Scrum emphasizes the importance of ensuring that work can be completed within the Sprint without external delays or bottlenecks.
upvoted 2 times
...
_AKay_
9 months, 1 week ago
Answer should be B. From scrum guide: They use word cohesive which means they are not independet. "If Scrum Teams become too large, they should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Goal, Product Backlog, and Product Owner."
upvoted 1 times
...
Jyoti1010
9 months, 2 weeks ago
Option A
upvoted 1 times
...
Godfall
10 months ago
Selected Answer: A
Based on the Scrum Guide, the key concern when multiple Development Teams are working from the same Product Backlog is: A. Minimizing dependencies between teams. Scrum emphasizes the importance of minimizing dependencies between Development Teams to allow for greater flexibility and agility in delivering increments of the product. This is mentioned in the Scrum Guide to ensure that teams can work independently and efficiently, contributing to the overall success of the product.
upvoted 3 times
...
Johnsonvibhute
10 months, 2 weeks ago
All of you read the question carefully..its asking about what seems to be a major concern qhen multiple teams are working on same PB, so each team can have different understanding so the concern is to get the right balance of requirements, the question isnt asking what the scrum master should do in this situation... please read the question carefully
upvoted 2 times
...
Dilara22
12 months ago
Selected Answer: A
I think the right answer is A
upvoted 2 times
...
azPSM
12 months ago
Selected Answer: A
selected answer A
upvoted 1 times
...
julioglez88
1 year, 1 month ago
Selected Answer: A
I suggest to vote instead of write that B is wrong, we must click on vote and select option A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in