Exam PRINCE2 Agile Foundation topic 1 question 5 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Foundation
Question #: 5
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should attend regular project progress meetings
  • B. The project board should make decisions based on the Agilometer risks
  • C. A project board member should fulfill the product owner role within a delivery team
  • D. The project board should increase the stage-level time tolerance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.prince2primer.com/directing-a-project-3/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
husnus
1 month, 2 weeks ago
Chatgpt also says A
upvoted 1 times
...
Djtomip
9 months ago
Selected Answer: A
Option A, "The project board should attend regular project progress meetings," is the correct statement about the 'directing a project' process in PRINCE2. The 'directing a project' process is one of the seven PRINCE2 processes that is responsible for providing overall direction and management for the project. The project board is responsible for directing the project, making key decisions, and ensuring that the project is delivered according to the project plan and business case. One of the key responsibilities of the project board is to attend regular project progress meetings to monitor the project's progress, review the project plan, and make any necessary changes. This helps ensure that the project is on track and that any issues or risks are addressed in a timely manner.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in