Exam CAPM topic 1 question 236 discussion

Actual exam question from PMI's CAPM
Question #: 236
Topic #: 1
[All CAPM Questions]

Which of the following are outputs of the Define Scope process in Project Scope Management?

  • A. Requirements documentation and requirements traceability matrix
  • B. Scope management plan and requirements management plan
  • C. Project scope statement and project documents updates
  • D. Scope baseline and project documents updates
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Andrew_1980
20 hours, 15 minutes ago
A - it's wrong as it's an output for Collect requirements process but not Define scope process
upvoted 1 times
...
041ba31
6 months, 3 weeks ago
C. Project scope statement and project documents updates The outputs of the Define Scope process in Project Scope Management are: Project Scope Statement: This document defines the project's scope, including its objectives, deliverables, constraints, assumptions, and acceptance criteria. It serves as a basis for making future project decisions. Project Documents Updates: The Define Scope process may result in updates to various project documents, such as the requirements documentation, assumptions log, constraints log, and other project-related documents. These updates reflect any changes or clarifications related to the project's scope definition.
upvoted 1 times
...
PeteyPete
8 months, 1 week ago
Selected Answer: A
The answer is A.
upvoted 1 times
...
missyi
1 year, 6 months ago
C is the correct answer.
upvoted 3 times
...
ale1231
2 years, 11 months ago
C. Project scope statement and project documents updates
upvoted 3 times
...
UlrichIng
3 years, 8 months ago
A. Requirements documentation and requirements traceability matrix is also OUTPUT
upvoted 1 times
...
UlrichIng
3 years, 8 months ago
C. Project scope statement and project documents updates
upvoted 3 times
...
MoonManBlue
3 years, 9 months ago
C-Project Scope Statement and Project Documents updates-5.3
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in