A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints.
Sprints can be measured as Integers only. So 1.5 & 2.5 are incorrect answers.
If sprint = 14 days, then 24 will be covered in 2 sprints
upvoted 1 times
...