Exam PMP topic 1 question 1351 discussion

Actual exam question from PMI's PMP
Question #: 1351
Topic #: 1
[All PMP Questions]

A bridge construction project has been paused due to a political change in the local government. After almost 5 years, the new government would like to resume the project, and a project manager is assigned.

What should the project manager do first?

  • A. Prepare an estimate of the time and cost to complete this project.
  • B. Study the project's lessons learned to understand why it was paused.
  • C. Meet the new stakeholders and understand their expectations.
  • D. Examine the project's business case in order to resume the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
c8ee0e6
9 hours, 15 minutes ago
The question says first thing and as per the choices, the PM will need to understand the new stakeholder's expectations.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in