Question #1 Topic 1

DRAG DROP -
During a gate review meeting, the deliverable was rejected by the customer.
Review the dashboard.
Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
Part 2: Select the proper document(s) to be updated.

Reveal Solution Hide Solution   Discussion   14

Correct Answer:

Question #2 Topic 1

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)

  • A. Train users on the proper use of the system.
  • B. Escalate the issue to the CCB.
  • C. Hold sessions to understand user challenges.
  • D. Track system usage and report user activity.
  • E. Log the issue in the project risk register.
  • F. Create a memorandum of acceptable use.
Reveal Solution Hide Solution   Discussion   11

Correct Answer: CE 🗳️

Question #3 Topic 1

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

  • A. Daily stand-up
  • B. Project momentum
  • C. Performance feedback
  • D. Meeting minutes
Reveal Solution Hide Solution   Discussion   10

Correct Answer: B 🗳️

Question #4 Topic 1

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

  • A. Evaluating the project
  • B. Releasing the resources
  • C. Closing the contracts
  • D. Reconciling the budget
Reveal Solution Hide Solution   Discussion   13

Correct Answer: A 🗳️

Question #5 Topic 1

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

  • A. Ishikawa diagram
  • B. Scatter diagram
  • C. Pareto chart
  • D. Decision tree
Reveal Solution Hide Solution   Discussion   4

Correct Answer: C 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in