Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
 

PMI CAPM Exam Actual Questions

The questions for CAPM were last updated on June 14, 2024.
  • Viewing page 1 out of 47 pages.
  • Viewing questions 1-10 out of 462 questions

Topic 1 - Single Topic

Question #1 Topic 1

Once the make-or-buy analysis is completed, which document defines the project delivery method?

  • A. Procurement statement of work (SOW)
  • B. Procurement strategy
  • C. Terms of reference
  • D. Change request
Reveal Solution Hide Solution   Discussion   20

Correct Answer: B 🗳️

Question #2 Topic 1

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

  • A. The project manager should identify and deal with stakeholders only during the execution phase.
  • B. Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • C. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • D. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Reveal Solution Hide Solution   Discussion   4

Correct Answer: B 🗳️

Question #3 Topic 1

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

  • A. Hybrid methodologies
  • B. Risk register updates
  • C. Outsourced project resources
  • D. Reliance on lessons learned documents
Reveal Solution Hide Solution   Discussion   10

Correct Answer: A 🗳️

Question #4 Topic 1

What should a project manager use to determine how much money is needed to complete a project?

  • A. Earned value management (EVM)
  • B. Estimate at completion (EAC)
  • C. Earned value analysis (EVA)
  • D. Budget at completion (BAC)
Reveal Solution Hide Solution   Discussion   13

Correct Answer: C 🗳️

Question #5 Topic 1

The project manager is creating the communications management plan. Which group of inputs is required to begin?

  • A. Work performance reports, change requests, and risk register
  • B. Work performance data, project documents, and stakeholder engagement plan
  • C. Project charter, project management plan, and project documents
  • D. Work performance data, stakeholder register, and team management plan
Reveal Solution Hide Solution   Discussion   8

Correct Answer: C 🗳️

Question #6 Topic 1

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

  • A. create the project management plan.
  • B. identify the project objectives.
  • C. review and update stakeholder engagement.
  • D. create the schedule baseline.
Reveal Solution Hide Solution   Discussion   8

Correct Answer: C 🗳️

Question #7 Topic 1

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.
How many communication channels are available?

  • A. 8
  • B. 18
  • C. 36
  • D. 40
Reveal Solution Hide Solution   Discussion   7

Correct Answer: C 🗳️

Question #8 Topic 1

A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?

  • A. Review stakeholder register and meeting
  • B. Data analysis and communication skills
  • C. Data gathering and data analysis
  • D. Communication skills and cultural awareness
Reveal Solution Hide Solution   Discussion   14

Correct Answer: B 🗳️

Question #9 Topic 1

Select three processes that are associated with Project Schedule Management? (Choose three.)

  • A. Define Activities
  • B. Plan Resource Management
  • C. Estimate Activity Durations
  • D. Develop Schedule
  • E. Acquire Resources
Reveal Solution Hide Solution   Discussion   4

Correct Answer: ACD 🗳️

Question #10 Topic 1

What are the project management processes associated with project quality management?

  • A. Plan Quality Management, Manage Quality, and Control Quality
  • B. Plan Quality Management, Manage Quality, and Cost of Quality
  • C. Manage Quality, Customer Satisfaction, and Control Quality
  • D. Customer Satisfaction, Control Quality, and Continuous Improvement
Reveal Solution Hide Solution   Discussion   5

Correct Answer: A 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in